Standby generator on a new pad with the conduit trench still open beside it, Castles Electrical, Norfolk, VA

Master Electrician & Class B Licensed

Commercial Generator Installation in Norfolk, VA

Norfolk’s zoning ordinance gives commercial projects credit for backup power. The Resilience Quotient point table for non-residential development lists a standby source that keeps a whole project operating, a generator that keeps critical operations going, and a written plan for moving to backup power and back again.

On a Norfolk build or redevelopment, Castles Electrical plans the Generac commercial-line standby generator and automatic transfer switch so the electrical side lines up with the backup power item your design team puts on the site plan.

Generac Authorized Dealer Master Electrical & Alternative Energy License #2710048784 Class B Contractors License #2705166194 Google 5.0 Rated Licensed Electricians, Never Subcontracted Free Installation Estimates
Licensed. Insured. Trusted. We treat your home like it’s our own.
Locally Owned in Virginia Beach Since 2012 Serving Virginia Beach & Nearby Cities
GENERAC
TESLA
KOHLER
NABCEP
BBBA+
SquareD
GENERAC
TESLA
KOHLER
NABCEP
BBBA+
SquareD
Home / Norfolk, VA / Commercial Generator Installation in Norfolk

01 — Why Castles

What Your Design Team Gets From Us

Matched to the Table Item

Transfer configured for the backup power item your design team is pursuing.

A Sequence You Can Write Down

Commissioning your staff watches, so the procedure reflects the real system.

02 — Point Table

Where Backup Power Appears in Norfolk’s Zoning Ordinance

Section 5.12 calls for proposed development to be reviewed for how it adds to resilience, and energy resilience is one of the things site plan review weighs, alongside reducing flood risk.

For non-residential development, Section 5.12.7 provides a point system in place of the site plan review. The ordinance calls it a menu: a project picks activities from three components, Risk Reduction, Stormwater Management, and Energy Resilience, and has to reach a minimum score in total and within each component.

Minimum scores grow with building size

The minimum rises with total building size: 3 points under 10,000 square feet, 4 from 10,000 to 25,000, 6 from 25,000 to 50,000, and 10 above that. Each component needs at least 1 point in the smallest tier, 1.5 in the two middle tiers, and 2 in the largest.

Backup power is scored as risk reduction

The three power items sit in the Risk Reduction component, next to wind-load design and building elevation. In a mixed-use project, the non-residential table applies only to the non-residential portion.

Electrical panel in the corridor of an existing Norfolk building

03 — Does It Apply

Many Generator Retrofits Fall Outside the Point System

Older buildings often sit outside the system. Work on a building constructed before March 1, 2018 is exempt if the cost of the renovation is under half its appraised value, or if an expansion adds under 50 percent of its floor area. Individually listed historic buildings, Norfolk Historic Landmarks, and contributing structures in listed or local historic districts are exempt as well.

New buildings or redevelopment that reach LEED Gold or above are also exempt. For everyone else, the review occurs during a rezoning, conditional use permit, site plan review, or Zoning Certificate review, whichever applies to the project.

The 2,500-square-foot line

Section 2.4.18 calls for site plan review before a Zoning Certificate for new construction, substantial improvements, and additions with 2,500 square feet or more of land disturbance. Any land disturbance over 2,500 square feet calls for it as well. Adding a standby generator to an occupied, older building often requires building permits and inspections rather than a site plan review, but the city decides which path your project takes, and we ask before the scope is set.

04 — Two Point Values

Whole-Facility or Critical Operations: 1.50 Points or 0.50

Table 5.12.7 gives 1.50 points for at least one alternative, independent source of electricity that leaves the project fully capable of operating when primary power is interrupted. A generator sufficient to keep critical operations functional during a power failure earns 0.50.

Those two descriptions match the two ways we set up commercial transfer. A whole-facility design sizes the generator and transfer equipment to the building’s full operating load. A critical-operations design starts from the circuits the business has decided it must keep, separates them onto their own transfer equipment, and sizes the unit to that list.

Load management can let a right-sized generator carry more than the critical list. Whether a given design counts as fully capable of operating is for the Zoning Administrator to decide. Section 5.12.4 says the ZA determines whether proposed activities meet the ordinance, in writing where practicable, so we describe the configuration to your design team and leave the point question with the city.

Question
Independent source, project fully operating
Generator for critical operations
Points in Table 5.12.7
1.50
0.50
Transfer setup we install
Whole-facility transfer configuration
Critical-loads transfer configuration, often with load management
Where sizing starts
Load calculation on the full operating load
Load calculation on the chosen critical circuits

05 — Process

Where We Fit in a Norfolk Project Schedule

01

Project scope

We ask whether backup power is part of the point score or a stand-alone addition.

02

Load calculation and configuration

Whole-facility or critical-operations transfer, with load management where it fits.

03

Placement and height

Pad location, the 8-inch baseline or higher elevation the plan calls for, and gas meter and line capacity or propane sizing checked with the plumbing company we partner with.

04

Set, wire, and inspect

The pad-set unit and automatic transfer switch go in, with the tie-in sequenced around business hours.

05

Transfer sequence recorded

The transfer sequence is run and recorded, a walkthrough of what the generator carries, and warranty registration.

Generac generator control board, where the controller’s timing settings live

06 — Loss-Of-Power Procedures

The Half Point for Written Loss-of-Power Procedures

Another 0.50 in the table goes to operating procedures for how the project will handle loss of grid power, move to a backup source, and return to normal operation. Those are three separate moments, and each depends on facts about the electrical system that the people writing the procedure need in hand.

When utility power drops

Generator controllers store timing settings in a written sequence. One Generac liquid-cooled line, for example, starts on utility failure after a programmable delay and warms up briefly before it takes the load.

What runs on backup

The procedure should name the panels or circuits the generator carries, so staff knows which equipment will stay on and which will stay dark until the grid returns.

When the grid comes back

The same literature lists a 1-minute engine cool-down. At commissioning, we run a simulated outage transfer test with your staff watching, so the owner or design team can write the procedure from what the system actually did.

07 — Equipment Height

The 8-Inch Baseline for Commercial Equipment

Section 5.12.7 establishes a baseline for every non-residential project covered by the Resilience Quotient: all significant electrical and mechanical equipment, along with the lowest habitable floor, is at least 8 inches above the highest adjacent grade, unless the flood overlay district requires a greater elevation. Our page on flood district elevation rules for generators explains how that overlay works. A standby generator and its transfer equipment would normally be treated as a single unit.

The table also scores going higher: 1.00 point for raising the ground story and that equipment to at least 3 feet above highest adjacent grade, or to elevation 11 (NAVD ’88), plus 0.50 for each added foot.

FEMA’s 2013 guide to floodproofing non-residential buildings lists emergency generators and emergency fuel supplies among the utilities typically found in critical core areas, alongside components that cannot be moved or elevated. We settle on pad height, conduit routes, and the gas line run on the site plan before a pad-set unit is ordered. The line is installed and connected by a partner plumbing company, working to the route we set together.

Commercial meters and disconnects mounted on a raised concrete base at a building wall
Castles Electrical electrician working at a standby generator on its pad

Castles Electrical

Licensed, insured, and locally owned. The work is done by our own electricians, never subcontracted.

08 — After Approval

Once a Generator Earns Points, It Stays Part of the Plan

Section 5.12.4 states that approved resilience activities must be installed, maintained, and kept in place, and treats failure to do so as a violation. A generator or procedure that earned points stays part of the approval.

That makes upkeep worth planning at installation. We register the Generac warranty when the unit goes in, back our installation with a workmanship warranty, and give guidance on maintenance and monitoring.

09 — Proof

Work Done Alongside Other Trades

One customer’s review describes working in conjunction with a whole-home siding project and making sure everything was up to code, including new wires run between exposed studs.

From our five-star Google reviews

Castles Electrical electrician going over the job with a customer at the door
Conduit and new wiring run along a commercial ceiling alongside other trades

Google 5.0 Rated by Hampton Roads Customers

Castles Electrical maintains a 5.0 rating on Google. The reviews below load as a live widget, so this page shows current feedback from real Castles Electrical customers.

Leave Us a Google Review

10 — FAQS

Norfolk Commercial Generator FAQs

Is backup power the only way to earn Risk Reduction points?+

No. It sits on the menu beside wind-resistant design, higher floor elevations, and flood protection for critical facilities, and a project can reach its minimums with other listed activities instead.

Our building is in a historic district. Does the point system apply?+

Only if the building qualifies. Section 5.12.2 exempts individually listed buildings, Norfolk Historic Landmarks, and structures noted as contributing in a listed or local historic district; a non-contributing building in the district is not exempt. Exterior work on those properties may still require a separate historic review, so ask the city before finalizing the generator location.

Can one project earn both the 1.50 and the 0.50 generator points?+

That is the Zoning Administrator’s call. We can describe what the installed system powers so your design team can present it to zoning.

Can a Norfolk project use a backup power option that is not listed in the table?+

Section 5.12.8 authorizes the Zoning Administrator to authorize minor deviations for good cause and to assign points to alternative activities, and the ZA maintains an online log of approved alternatives. Your design team can check that log for similar projects.

What proof does the city accept for items an inspector cannot see?+

Section 5.12.4 states that documentation for items that cannot be visually verified during an inspection may take the form of invoices, receipts, or delivery confirmations. Keep the generator and transfer switch paperwork with the project records.

Ready When You Need Us

Planning a Norfolk Building With Backup Power?

Send the project address, where the site plan is located, and which backup power option your design team is considering, and we will set up a site visit.

Office and hours

Based at 2984 S Lynnhaven Road, Suite 104, Virginia Beach, VA 23452.

  • Monday to Friday: 7:00 AM to 10:00 PM
  • Saturday: 7:00 AM to 7:00 PM
  • Sunday: Closed
  • After-hours voice messages are checked, and we take emergency and after-hours calls when we can

The backup power item on your site plan is built the way the plan describes it.

Castles Electrical electrician reviewing the job with a homeowner